Position evaluations

With the position-related construction site evaluations you receive a target / actual comparison between the pre-calculated and actually posted material quantities, times and costs at item level.

The data basis is formed by the quantities or times planned in the preliminary calculation and the bookings recorded in the final calculation. Both target and actual performance units are made from the Mass list or the order quantity. The actual quantity comes from the post-calculation postings. The target quantity comes from the quantity and time estimates of the preliminary calculation per service unit.

Under Position evaluations the following prints are available.

Costs
Prints an item-by-item list of the individual costs, the manufacturing costs, the DB and the proceeds, as well as the difference between the order and the actual status.
All or selected positions are considered. In addition, items can be output without post-costing or pre-costing values.

Material
Prints a position-based target / actual comparison for material for a construction site.
All or only selected items are printed.

Times
Prints an itemized target / actual comparison for wages and equipment for a construction site.
All or only selected items are printed.

Further steps