Times

Description

Position evaluation times you receive a position-related comparison between the planned time approaches from the preliminary costing and booked times for wage and device hours. The position evaluation is carried out for a construction site. Note that for a meaningful evaluation, the posting of times in the daily report entry must take place at item level (assignment to item).

Application

Open within the Post calculation the menu Print and choose in the group Position evaluations the entry Times.


The following print menu opens.


Calculation example:
Service units 1.000, service unit m² = planned quantity 1.000 m² (item quantity 1.000), order quantity 800 m²

Name Feld BUSINESS Preliminary calculation Post calculation Soller Is
Service unit quantity Item quantity 1.000 * 1m² = 1.000m² 800m² 800m²
Unit of measure per service unit [ME / LE] Time estimate for preliminary calculation 20 min 20 min 12,5 min (calculated)
(Time) amount 1.000 * 60 min = 20.000 (calculated) 10.000 min 16.000 min (calculated) 10.000 min

Print settings

Make the following settings:

Variant
For each form you can use the designer to create different Print variants shape. By clicking select the variant that you want to use for the printout.

Contact Person
The name of the logged in user is preset, which you can enter in Address manager in the user data.

output
By clicking choose whether to print or save the list as a Fax or e-mail want to send.

printer
By clicking choose the printer you want to use for printing. Only printers installed under Windows are available for selection.

Paper feed
If your printer offers several paper trays, select by clicking on the slot from which the paper is used for printing.

print from / to page
Here you can specify the pages to be printed out. If you want to print the entire list, please do not make any changes in this field.

Copies
If you need several copies of the list, enter the desired number here.

Settings tab

Activate the respective option by ticking the box .

Construction site
All construction sites with the LV status are in the project tree BA (Construction site, work not yet started) and BB (Construction site, work started) to choose from. Select the construction site or several construction sites for which you want to print the construction site result.

A quick search is available below the project tree to quickly find a construction site. To do this, enter in the field Keyword one or parts of a course number, a course description or a client name and start the search with Enter. A full text search is carried out by entering a space in front of the search term.

Quantities from
Here you specify whether the quantities from the order, the quantity approach or from quantity statements should be used for the comparison calculation of the preliminary costing prices.

All positions
All positions are taken into account. However, if you want to limit the selection, go to the tab positions and mark with which positions you want to consider.

Print the cover sheet only
A summary of the target / actual comparison is also printed out (wage or device designation, target hours, actual hours, difference in quantity).

Print preview and printing

After you have entered all the necessary information for your printout, click in the menu Print settings on to see a print preview. Send the printout to the printer by clicking on or alternatively use the key combination Ctrl + P.

Further steps